Table of Contents

SECTION 8
REGULATORY AND ENVIRONMENTAL ISSUES RELATED TO PRODUCED WATER

Much of the following information was taken from the Environmental Handbook produced cooperatively by the Oklahoma Midcontinent Oil and Gas Association and the Oklahoma Corporation Commission. Also, the General Rules and Regulations of the Arkansas Oil and Gas Commission were reviewed to include information pertaining to Arkansas.

Oklahoma and Arkansas have assumed primary responsibility for enforcing Environmental Protection Agency (EPA) regulations pertaining to the construction, operation and closure of Class II injection wells within their respective states.

Injection and Disposal Wells.  General requirements.  Approval and permits must be obtained from the Oklahoma Corporation Commission (OCC) or the Arkansas Oil and Gas Commission (AOGC) for any new injection or disposal well.

A Mechanical Integrity Test (MIT) must be performed at least once every five years and initially before a well is used. In Oklahoma the initial test must be witnessed by an authorized representative of the Oil and Gas Division and results submitted on Form 1075 within 30 days by the operator. In Arkansas, within fifteen (15) days after the completion of the well, a completion report, well logs, and injectivity test performed on the well must be filed with the Oil and Gas Commission. The AOGC must be notified in writing before the beginning of injection to allow inspection of the well and conduct the initial mechanical integrity testing.

Minimum standards for injection and disposal wells are:

  • Oklahoma. Injection must be through adequate tubing and packer.

  • Arkansas. All injection wells must have tubing and packer “or other installation” to protect the casing.

  • A 1/4 inch female fitting in Oklahoma (1/2 inch in Arkansas) with cut-off valve to the tubing is required to be installed so injection pressure may be checked.

  • Oklahoma. The packer must be set within 20 feet of the packer setting depth as described in the permit to inject.

  • Arkansas. The packer can be set no higher than 100 feet above the injection interval.

  • Minimum cement height circulated above the injection zone in the annulus between the casing and the borehole must be 250 feet.

  • Oklahoma. The packer must be set at least 50 feet below the depth of the top of cement behind the production casing.

  • Oklahoma. Surface casing must be set at least 50 feet below the base of treatable water or 90 feet below the surface (whichever is greater) if a stage collar is set or the production casing is cemented to the surface (unless otherwise authorized),

  • Arkansas. New disposal wells require surface casing to be set 250 feet below the lowermost  Underground Sources of Drinking Water (USDW).

  • Oklahoma. Surface casing must be set at least 200 feet below the base of treatable water for annular injection of drilling fluids.

  • Arkansas. A sign must be maintained at the well site to indicate operator, well name, well number and location description.

Oklahoma.  Any newly drilled or converted injection or disposal well within ˝ mile of any active or reserve municipal water supply well will not be approved without notice and hearing and the operator must prove that the water well will not be impacted. Applications for newly drilled or converted injection or disposal wells need to be filed with the Underground Injection Control Department on Form 1015. Applications must be accompanied by a plat showing the location and total depth of all wells within 1/4 mile of the injection or disposal well, and all surface owners and operators of producing leases. A copy of the application must be delivered to the surface owner of the land on which the well will be located and to each operator of a producing lease within ˝ mile of the well. A notice also has to be published in an Oklahoma City newspaper and a newspaper in the county where the well will be located. If a written objection is filed within 15 days, a hearing will be set at the OCC.

Arkansas. Applications are filed with the Oil and Gas Commission on a form titled “Application to Inject Salt Water/ Enhanced Recovery Fluid”. Arkansas requires a plat indicating the location of the proposed injection well with distances to the nearest lease lines, including all wells of public record and fresh water wells of public record within ˝ mile radius from the proposed injection well. Arkansas also requires a separate list of all wells which have penetrated the injection zone that indicates: 1) exact legal location, 2) current operator, 3) lease name, 4) name of zone currently completed, 5) perforated intervals, 6) total depth, 7) drilling date, 8) cementing records, 9) record of completion/plugging, and 10) current status. Information on this list MUST agree with AOGC records. You are required to attach a notarized copy of the proof of publication of the application as it ran in one publication in a legal newspaper having a general circulation in the county or in each county, if there shall be more than one, in which the lands embraced within the application are situated, and by mailing or delivering a copy of the application to each operator of producing or drilling wells within one-half (1/2) mile radius of the injection well. Such notice shall be published, mailed or delivered at least ten days, but no more than 30 days, prior to the date on which the application is mailed or filed with the Commission.

Monitoring and reporting.  Oklahoma.  Operators must monitor and record the injection rate and surface injection pressure monthly. For each calendar year, the operator is required to report the results of monthly monitoring on Form 1012A by April 1 of the next year. Operators must submit Form 1072 (Notice of Commencement or Termination) within 30 days after injecting or disposing into a well. When a mechanical failure or downhole problem occurs, the operator must notify the OCC Field Inspector within 24 hours after discovery. A written repair plan must be submitted within 5 days.

Arkansas.  Operators must monitor and submit a saltwater disposal report monthly on AOGC Form 14. The report must be filed no later than the 15th of the month following the month covered by the report. Required monthly injection data includes barrels of water injected, barrels of cumulative water injected, injection pressure on the tubing and annulus and injection zone.

Oil and Produced Water Spills.  General requirements for Oklahoma.  The first critical activity is to safely contain and control the spill to protect human safety and minimize damage to the environment. Notify proper authorities, including the appropriate OCC district office before cleanup (see below under reporting requirements). Attempt to recover and remove oil if possible. Cleanup contaminated soil, vegetation, and/or water as per acting authority requirements. Saltwater or oil soaked soil may require sampling before remediation can take place.

Reporting requirements for Oklahoma.  Report spills to the following Oklahoma Corporation Commission District Offices:

  • Bristow             (918) 367-3396

  • Kingfisher         (405) 375-5570

  • Duncan             (405) 255-0103

  • Ada                  (405) 332-3441

Report verbally to the Commission District Office or Field Inspector within 24 hours of discovery of a reportable quantity spill. Failure to report may result in a $500 fine. File a written or oral report with the District Office within 10 working days. For spills that impact surface waters of the state (rivers, streams, lakes) also report the spill to:

  • Oklahoma Department of Environmental Quality            (800) 522-0206

  • National Response Center                                            (800) 424-8802

Spills that pose an imminent danger to fish or wildlife should be reported to the Oklahoma Department of Wildlife Conservation.

Record keeping for Oklahoma. Maintain adequate records of each non-permitted discharge reflecting the information, time and manner of reporting. Produce such documents upon demand by an authorized representative of the Commission. Records of all reportable spills should be kept on file in the nearest company office. Document all cleanups and notifications.

Reporting requirements for Arkansas.  Operators should immediately report to the Arkansas Oil and Gas Commission any breaks or leaks in or from tanks or other receptacles and pipelines from which oil or gas is escaping or has escaped. The report must contain the location of the well, tank, receptacle, or line break by Section, Township, Range, and property, so that the exact location can be readily located on the ground. The report shall also specify what steps have been taken or are in progress to remedy the situation reported and shall detail the quantity (estimated, if no accurate measurement can be obtained, in which case the report shall show the same is an estimate) of the oil or gas lost, destroyed, or permitted to escape. In case any tank or receptacle is permitted to run over, the escape thus occurring shall be reported as in the case of a leak. The report as to oil losses is necessary only in case such oil loss exceeds twenty-five (25) barrels in the aggregate.

Spill Prevention, Control and Countermeasure (SPCC) Regulation.  (At the time of publication of this handbook, due to industry pressure, EPA has indicated its intent to extend the February 17, 2003 compliance date and the August 2003 compliance date for SPCC Plan revisions. EPA indicated it would simultaneously issue a direct final rule and a proposed rule to extend the compliance deadlines for one year with a mechanism to extend beyond that time. Following action on the deadline extension, EPA indicated it will initiate efforts to assess the problems with the new regulations and determine methods to resolve them through additional rule making, guidance, or interpretation. Keep in touch with your trade associations for future updates regarding these new regulations.)

On July 17, 2002, the EPA amended the Oil Pollution Prevention regulations promulgated under the authority of the Clean Water Act. This includes new requirements for SPCC Plans and for Facility Response Plans (FRPs). The rule became effective August 16, 2002. The revised rule is difficult to read and understand. The following paragraphs attempt to summarize requirements for onshore oil operators.

It has been determined that many oil drilling and production facilities are subject to the SPCC regulation. EPA’s SPCC regulation (40 CFR 112.1 through 112.7) applies to nontransportation-related facilities that could reasonably be expected to discharge oil into or upon the navigable waters of the United States or adjoining shorelines, and that have 1) any single container or group of containers each greater than 55 gallons having a total capacity of greater than 1320 gallons, or 2) a total underground buried storage capacity of more than 42,000 gallons.

The SPCC regulation requires the facility owner/operator to prepare an SPCC Plan for their facility. All existing SPCC Plans prepared before August 16, 2002 must be revised on or before February 17, 2003 to comply with the new rules and implemented by August 18, 2003. If a facility becomes operational after August 18, 2002, but before August 19, 2003, an SPCC Plan must be prepared and implemented by August 18, 2003. If a facility becomes operational on or after August 19, 2003, a plan must be prepared and implemented before the facility goes on stream. There is a provision to apply for an extension for the plan preparation time.

Additionally, a Professional Engineer must certify the SPCC Plan and attest:

  • The Professional Engineer is familiar with the SPCC rule.

  • The Professional Engineer or agent has visited and examined the facility.

  • The SPCC Plan has been prepared in accordance with good engineering practices and the SPCC rules.

  • Rules specifying procedures for inspecting and testing are included.

  • The SPCC Plan is adequate for the facility.

The revised plan must be retained at the facility, if the facility is attended at least four hours per day on a regular basis.

General requirements.  The SPCC Plan must include:

  • a physical layout of the facility, including location of each tank, separator, heater treater, transfer piping and pumps;

  • type of oil in and the capacity of each tank and vessel;

  • discharge prevention measures appropriate for routine loading, unloading and transferring oil within the facility;

  • discharge and drainage controls such as secondary containment, catchment basins, retention basins and control procedures;

  • estimated direction, rate and total quantity of release flow;

  • a method planned for discovery, response, and cleanup by company and contractor; disposal methods for recovered oil;

  • a list of contractors with phone numbers for company response coordinator, National Response Center, cleanup contractors with whom the company has a response agreement; and

  • a list of Federal, State and local agencies.

The owner/operator of onshore production facilities must have at least one of the following means of secondary containment for tanks, treating vessels, piping, and pumps:

  • dikes, berms, retaining walls

  • curbing

  • culverts, gutters or drainage systems

  • weirs, booms or other barriers

  • diversion ponds

  • retention ponds

  • sorbent materials

For tank truck or tank car loading/unloading area racks (frames), use catchment basins or treatment systems designed to handle discharge from the largest single truck compartment or use a quick drainage system. Provide secondary containment for tank batteries, separators, heater treaters, transfer pumps and interconnecting piping. The secondary containment must hold the capacity of the single largest tank and anticipated precipitation. Newly installed or repaired buried pipes must be coated and wrapped. Provide secondary containment for flowlines, e.g., double-walled pipe, berms, catchment basins, and booms. If the installation of secondary containment as discussed above is not practical and the facility does not have a Response Plan, the owner/operator must include in the SPCC Plan:

  • an explanation why the controls are not practical

  • periodic, scheduled integrity testing of facility containers, valves, piping (including flowlines)

  • a Contingency Plan

Additionally, the SPCC Plan must include:

  • a written commitment of manpower, equipment and materials to control and remove released liquid hydrocarbon.

  • a written inspection and testing procedures for tanks, separators, heater treaters and piping. The procedures and record of inspections and tests must be signed by the appropriate foreman and retained with the SPCC Plan for three years.

  • a written commitment to train all oil-handling company personnel regarding

    • maintenance and operation of equipment to prevent oil releases,

    • release reporting and control,

    • pollution control statutes, rules and regulations,

    • general facility operations,

    • SPCC contents.

  • a provision to schedule and conduct annual release prevention briefings for oil-handling personnel. Include and describe known releases, equipment failures or malfunctions and recently developed precautionary measures to prevent releases.

  • a designated employee who is responsible for oil release and who reports to the facility management.

  • a requirement to seal all tank and vessel valves when not in use and the facility is operating.

  • a lockout in the off position for all shipping and transfer pump electric start controls when not in use.

  • a way to cap, plug or flange all open-ended liquid hydrocarbon pipes and/or valves when not in use or when in extended standby service.

  • provision for facility lighting, if practical.

Specific requirements.  An onshore producing facility reasonably expected to release liquid hydrocarbons that could enter waters of the United States, must prepare an SPCC Plan in accordance with the General Requirements for the SPCC Plan plus the following provisions:

  • Dikes and drains must be closed and locked when not in use. Oil-free rainwater may be drained to the ground, but the owner/operator must inspect the rainwater for oil before discharging the rainwater. If oil is present, the oil must be removed and returned to the oil treating system or disposed of.

  • Written inspection and testing procedures for tanks, separators, heater treaters and piping must be maintained. The procedures and record of inspections and tests, signed by the appropriate foreman, must be retained with the SPCC Plan for three years.

  • Provide secondary containment for all tanks, separators, heater treaters and transfer or shipping pumps. The containment must be capable of retaining the capacity of the largest single tank and anticipated precipitation. The owner/operator may use catchment basins in lieu of berms.

  • The owner/operator must maintain written regularly scheduled drainage system (borrow ditches, stream, ravines) inspection instructions. Oil must be removed, if discovered.

  • Design new and update old tank batteries in accordance with good engineering practice to prevent releases. At a minimum:

    • tank size must be adequate to assure no overfill if lease operator is delayed

    • equalizer lines between tanks must be present

    • vacuum protection to prevent tank collapse must be present

    • high level sensor alarms must be present for computerized facilities.

  • The owner/operator must maintain written regularly scheduled inspection procedures for above-ground tanks, piping, valving, pumps, drip pans, polish rod, stuffing boxes.

  • Written inspection records of produced water disposal facilities must be maintained, particularly after a sudden change in atmospheric temperature.

  • Written flowline maintenance program must be prepared.

As mentioned previously, the above is an attempt to summarize the new rules for onshore oil operators. There are also new rules for onshore drilling and well servicing, as well as offshore drilling, producing and well servicing. No matter who ends up preparing an SPCC Plan, remember that ultimately it is the owner/operator who is responsible for complying with the regulation. A copy of the regulation is available by calling or writing your nearest EPA office. For Oklahoma and Arkansas:

            SPCC/FRP Coordinator

            U.S. EPA-Region VI (6SF-RP)

            1445 Ross Avenue

            Dallas, TX 75202-2733

            (214) 665-6489

Cleanup Guidelines.  Follow the most recent "Oklahoma Corporation Commission Guidelines For Responding To and Remediating Spills". Current guidelines are as follows:

Crude oil spill to soil.  Use temporary dikes and emergency pits to confine the spill to the smallest possible area. All accumulated oil should be collected and recycled. Absorbent materials may be used to collect free oil. Contaminated soil may be removed and replaced with compatible soil and the contaminated soil land applied in accordance with OCC-OAC Rule 165:10-7-26.

If on-site bioremediation of the contaminated soil is the preferred option, then the soil brought to the surface should be disked to a depth of six inches and fertilized by applying 160 pounds of nitrogen, 40 pounds of phosphorus and 40 pounds of potassium per acre, unless soil testing reveals that an alternative ratio of these nutrients would be superior for the purposes sought. If weather and soil conditions do not permit immediate disking, it may be necessary to burn the material following Department of Environmental Quality (DEQ) approval. Disking and fertilizing should be done as soon as weather conditions permit.

All affected areas must be restored as near as practicable to the level of land productivity that existed before the spill occurred and may require additional disking, fertilizing and/or revegetation. Any alternative reclamation plan must be submitted to the OCC District Office for approval before implementation. If remediation cells or piles are to be utilized, remediation should be coordinated with the OCC Field Operations Department.

Waste management practices that can be utilized during the cleanup of crude oil spills include reclamation and/or recycling; road applications by County Commissioners; application to lease roads, well locations, and production sites; and disposal of waste oil by transfer or sale to a reclaimer/transporter/County Commissioner. Some of these practices require permits. (See OCC-OAC Rule 165:10-7-24).

Salt water spill to soil.  Because of the variable conditions that can be associated with saltwater spills to soil, it is difficult to provide absolute guidance as to the proper actions to take as a response to all spills. However, general actions that should be taken in all cases are as follows: 1) initiate actions to prevent further discharge or release; 2) utilize an appropriate containment system to minimize the surface area impacted by the spill. Such a system could consist of temporary diking, emergency pits, or leak proof tanks; and 3) remove free fluids from the spill surface as soon as practicable. The use of a vacuum removal system is one way such removal can be facilitated. In some cases, particularly where there is standing water or wet soils, flushing the spill areas with fresh water may be an appropriate method to facilitate the removal of saltwater from the soil surface. In any case, saltwater fluids recovered should be properly disposed. Permitted Class II disposal or injection wells are the only types of disposal that are appropriate.

After considering and weighing the relative conditions and importance of each of the remediation factors, it may be determined that it is appropriate to obtain soil samples to determine whether soil removal or other remedial measures may be needed. If soil samples are to be taken, a background soil sample from outside the spill area should be collected for the purpose of comparison. If the affected area is large, two or three soil samples should be collected towards the edge of the spill, followed by two or three soil samples near the center of the spill. Reduced sampling may be done for smaller areas.

Generally, quick response actions should limit the infiltration of such spilled fluids. In such cases, surficial samples (within one foot of the surface) may suffice for sampling purposes. If more than one week has passed since the time of the initial release, substantial rainfall has been received, or if plowed or sandy soils are present, soil samples should be collected to a depth of three to five feet or to bedrock if it is shallower. Such samples should be collected at one-foot depth intervals.

All soil samples should be placed in suitable containers for transportation, chain-of-custody records completed and the samples sent to a qualified laboratory. Once received, the samples should be analyzed for Total Dissolved Solids (TDS) or Total Soluble Salts (TSS). Sample analysis exceeding 2500 ppm for TDS (or TSS) indicates a need for remediation in place or removal of the soils in the area that such samples were obtained from.

If the option of remediation by leaching is selected, one can expect remediation to take from one year to several years, depending upon site conditions. Clay soils, in particular, do not leach well, so removal is normally recommended. For leaching, the affected area should be treated with 20 to 30 tons per acre of organic matter (either vegetable or animal) and an appropriate amount of calcium sulfate (gypsum) or calcium nitrate. To determine the appropriate amount, refer to the recommendations of the soils laboratory or a consultant. If more than five tons are recommended, the recommended rate should be split into separate applications three to six months apart. It is not unusual to have to repeat treatments in order to get good results.

If the removal option is selected, the area adversely impacted by the spill should be excavated to a depth sufficient to remove all soils that indicate a TDS (or TSS) level of 2500 ppm or greater. Excavated material may then be disposed of in a manner consistent with Corporation Commission Rule OAC 165:10-7-26 or 165:10-9-1. Following excavation, the area must be restored to its original use by backfilling with compatible replacement soil and establishing suitable vegetation as soon as possible.

Saltwater spill to surface water.  If possible, confine the spill to the smallest area possible by using temporary dikes and emergency pits. Collect as much of the affected water as possible and transport to an authorized disposal facility. Cleanup procedures can be discontinued when the affected water is restored to the previous beneficial use for the stream or body of water. All saltwater spills to navigable waters of the state should be reported to EPA Region VI, OCC, and the DEQ.

Crude oil spill to surface water.  Use temporary dikes, emergency pits, artificial barriers or floating booms to confine the spill to the smallest possible area. Containment barriers should be located for easy access and removal of oil. Floating oil should be immediately removed from the surface of the water by pumping or skimming. Removal must continue until there is no visible sheen on the surface of the water. Removal may require absorption of the oil with absorbent materials including straw or commercial absorbents.

Stream or impoundment banks and affected vegetation may be cleaned by washing or burning (following DEQ approval) to remove excess oil and staining if erosion can be prevented. After all of the oil has been removed from the surface of the water, containment structures should be left in place for capture of any residual product. These structures may be removed after there is no evidence of additional product accumulation. Sufficient time must be allowed for all oil to flush from the original spill area and there should be no residual sheen on the water.

Following removal of the containment structures, an effort should be made to restore the area to pre-spill conditions. All contaminated materials should be disposed of in a manner approved by OCC Field Operations. If the surface water is designated as a source of public water supply under Oklahoma Water Quality Standards, cleanup procedures must continue until all assigned beneficial uses for the stream or body of water are restored. All oil spills to navigable waters of the state should be reported to the National Response Center, OCC, and the DEQ.

Table of Contents